Sunday, July 2, 2017

Reducing Job Shop Costs versus Increasing Job Shop Throughput

Reducing Job Shop Costs

  I was just reading an article on CNCReport.com titled "Never Enough Magnetic Mounts".  The author was calculating how much money you'd save if you invested in some magnetic strips to make finding tools faster and easier.  Here's an excerpt from the article:
Hourly Pay Rate = $15 ($0.25/minute) Time spent looking for a tool = 5 minutes Times per week looking for a tool = 3 With these numbers in place it costs nearly $200 a year in lost time and money simply searching for a tool ($0.25 x 5 mins x 3 times a week x 52 weeks = $195). The math doesn’t lie so lets get some part numbers: McMaster-Carr: Magnetic Mount – $20 – 6613A24 Allen Wrench Set – $15 – 5709A52 Good Scissors – $9 – 7091A16 Box Cutter – $5 – 4927A11 Screwdriver Set – $14 – 5791A51 Spending about $70 will save time and $200. Did we miss anything?
YES!  But I don't disagree with the recommendation, only the justification. To determine if an investment of $70 is worth it, I would NOT calculate the cost savings as done in this article.  Why?  Because the reality is that your going to pay your people their hourly rate regardless of how they spend their time. You won't actually get a reduction in their hourly rate. Saving time is NOT ...

reducing job shop costs.

Instead, I would estimate how much additional Throughput you'd generate due to being able to reduceTime-is-NOT-money or eliminate time wasted looking for tools.  For most job shops and machine shops Throughput is sales minus raw material, outside processes, freight, and sales commission (if any).  Throughput is similar to margin but without direct labor.

Increasing Job Shop Throughput

For example, if you could ship one more $500 job per week and the Throughput on that job is $375, then you would easily and quickly recover the $70 investment with first additional job shipped (and paid for). BUT BE CAREFUL! When you're considering how much additional Throughput you'll get from an investment you have to be REAL.  If you put these magnetic strips at a non-constraint, the additional Throughput will be ZERO or very low. However, if you speed up your constraint, you can and will be increasing job shop throughput!

Job Shop Scheduling

Making sure that you have all the tools you need is part of getting "full kit" in Velocity Scheduling System.  VSS is for highly custom job shops and machine shops.  It is a visual, manual scheduling system.  My experience is that it usually pays to have full kit before releasing a job. Learn how -- check out the "How to Get More Jobs Done Faster" webinar.  In 47 minutes I explain how and why full kit along with other things can help you increase your Throughput with the same people and resources.  This, of course, means that your profits will increase.  And isn't THAT really The Goal? Wishing you success! By Dr Lisa Lang This article is copyrighted by Science of Business, Inc. All rights reserved. Visit our Re-post guidelines.

http://www.velocityschedulingsystem.com/?p=2212

Friday, June 2, 2017

Manufacturing Expert Dr. Lisa Lang Hits Amazon.com Best Seller List With “Trendsetters”

FOR IMMEDIATE RELEASE Manufacturing Expert Dr. Lisa Lang Hits Amazon.com Best Seller List With “Trendsetters” Dr. Lisa Lang, of the Science of Business, recently hit two separate Amazon.com best-seller lists with the new book Trend Setter cover“Trendsetters.” Orlando, Fla. – October 6, 2011 – “Dr. Lisa” Lang, President of the Science of Business, recently joined a select group of business experts and entrepreneurs to collaborate and co-write the business and marketing book titled Trendsetters: The World’s Leading Experts Reveal Top Trends To Help You Achieve Greater Health, Wealth and Success! The book was released by CelebrityPress™, a leading business, marketing and health book publisher. Trendsetters: The World’s Leading Experts Reveal Top Trends To Help You Achieve Greater Health, Wealth and Success! was released on Thursday, October 6, 2011 and features top advice from leading entrepreneurs, business owners and marketing experts from around the world. The authors tackle an array of subjects ranging from health, wealth, marketing and business success. Dr. Lisa contributed a chapter titled “Velocity Manufacturing” which is based on her Velocity Scheduling System Coaching Program for scheduling highly custom job shops and machine shops. On the day of release, Trendsetters reached best-seller status in two Amazon.com categories: Entrepreneurship and Direct Marketing. Dr Lisa was selected by the editor for an Editor's Choice Award for her Velocity Manufacturing chapter. And, after such a successful release she will be recognized by The National Academy of Best-Selling Authors™, an organization that honors authors from many of the leading independent best-seller lists. Dr. Lisa is the President of the Science of Business and has recently worked with Dr Goldratt who is the father of Theory of Constraints and author of The Goal. Science of Business specializes in increasing profits of highly custom manufacturers and job shops by applying Theory of Constraints, Lean and Six Sigma to operations with Velocity Scheduling System and to engineering with Project Velocity System and to marketing with Mafia Offers. About the Book: Are YOU a TRENDSETTER? By definition, a Trendsetter is not a follower. So, what is a Trendsetter? Is it a leader? Leadership can mean leading in thought, word or deed, or some combination of all three. In the Business World, thought has no future if bounded by inaction - commonly referred to as 'analysis paralysis' - so thought and deed are invariably intertwined. Now combine those two with the 'word' portion of the trifecta of thought, word and deed, and now...we have the prospect of leadership and success. So, are you a Trendsetter? You may be. There is no prescription for one, but you can compare your goals and achievements with the benchmarks made by those in this book. In this book, we give you a number of our Celebrity Experts® who are Trailblazers and Trendsetters. They have done it! These are successful experts who made their mark and share with you how they and their concepts developed. Can Trendsetting be emulated? Absolutely, but you, yourself, will have to personally work through the stages of thought, word and deed...just like these leaders have. May you be crowned by your definition of Success! What you get by achieving your goals is not as important as what you become by achieving your goals. ~ Zig Ziglar To order a copy of the book: http://www.amazon.com/dp/0983340463/ref=as_li_tf_til?tag=thescienceofb-20&camp=0&creative=0&linkCode=as1&creativeASIN=0983340463&adid=01VV9ZBERTVPK9EP6DN3 About Celebrity Press™: Celebrity Press™ is a business book publisher that publishes books from thought leaders around the world. Celebrity Press™ specializes in helping its authors grow their businesses through book publishing. Celebrity Press™ has published books alongside Brian Tracy, Dr. Ivan Misner, Ron LeGrand, Mari Smith, Kelly O’Neil, Alexis Martin Neely and many of the biggest experts across diverse fields. ### keywords: Dr Lisa Lang, Dr Lisa, Velocity Manufacturing, custom manufacturing, Theory of Constraints, Velocity Scheduling System, Science of Business, CelebrityPress, business book, marketing book, business book publisher, marketing book publisher, business book publishing company

http://www.velocityschedulingsystem.com/?p=1228

FREE Webinar on Job Shop and Machine Shop Scheduling

This webinar replay is on exactly how to Get More Jobs Done Faster. It is NOT theory but a specific "how to". This is the same program recommended by Westinghouse to their vendors and recommened internally to Schlumberger plants. To participate LIVE in one of these webinars and to get YOUR questions answered, sign up here: https://www.velocityschedulingsystem.com/webinar/ Space is limited to to ensure we get all your questions answered. (replay no longer available, please sign up for our next webinar) If you're looking to  improve your scheduling and you own or run a job shop or machine shop, you don't want to miss these insights!  This video will be taken down, so watch while you can. Dr Lisa Lang (know as Dr Lisa) will be your webinar presenter.  She is a Theory of Constraints expert and recently worked for Goldratt Consulting owned by Dr Eliyahu M Goldratt, author of The Goal and father of Theory of Constraints.  Dr Lisa developed the Velocity Scheduling System Coaching Program to hand hold companies through the process of implementing the Theory of Constraints scheduling technique called Drum Buffer Rope. Leave your questions on Velocity Scheduling System Coaching Program and tell me what you thought of the webinar.   Did you like it?  Did it answer any questions for you? CLICK THE COMMENT LINK ABOVE!!

http://velocityschedulingsystem.wordpress.com/?p=298

Theory of Constraints Velocity Scheduling System Webinar

WEBINAR:  How to Get More Jobs Done Faster

Each webinar covers  exactly how to get MORE Jobs Done Faster.  We cover how scheduling is traditionally done and then we cover the Velocity Scheduling System approach.  During the webinar you learn what to go do TOMORROW! Sign up here: https://www.velocityschedulingsystem.com/webinar/ WARNING: The Velocity Scheduling System Coaching Program is NOT training. This is a go and do program. Only job shops ready to improve due date performance, cut lead-time through thier shop and who seriously want to reduce chaos should sign up. Velocity Scheduling System is based on Goldratt Theory of Constraints Drum Buffer Rope and is for job shops looking for a better way to schedule their shop.

http://velocityschedulingsystem.wordpress.com/?p=449

Manufacturing Expert Dr. Lisa Lang Discusses Theory of Constraints in The Fabricator

FOR IMMEDIATE RELEASE  Manufacturing Expert Dr. Lisa Lang Discusses Theory of Constraints in Article  Dr. Lisa Lang, inventor of the Velocity Scheduling System, featured in a November 2011 article discussing her expertise in Theory of Constraints  Green Valley, AZ – October 10, 2012 – “Dr. Lisa” Lang, President of the Science of Business and inventor of the Velocity Scheduling System is featured in a November 2011 article in The Fabricator and TheFabricator.com, where she was interviewed about Theory of Constraints and Velocity Scheduling System.  The article also highlights two of Dr. Lisa’s clients, CMI Industry America and Guntert & Zimmerman.  The article, titled “High mix, fast delivery--on time: How high-mix, low-volume fabricators adapt the Theory of Constraints,” was written by Tim Heston.  Tim Heston explores how Dr. Lisa helped both clients utilize the Theory of Constraints to keep the chaos of their manufacturing in check, but allow for dealing with emergencies while increasing productivity. Dr. Lisa remarks on the negatives of focusing on efficiency.   Below is an excerpt:

 TOC goes against traditional manufacturing thinking, in which workers produce more than is needed to reduce the number of setups and maximize the efficiency of all resources. The forecast, after all, says these parts will be needed eventually, so why not produce them now? The problem is, of course, that sales forecasts are notoriously inaccurate, so those parts may never be needed. Also, producing so many unneeded parts floods the floor with work-in-process (WIP), while jobs in queue sit for days or weeks waiting for large batches to work their way through.

 Dr. Lisa offers her expertise throughout the article, which explores five main topics: “The Value of Throughput,” “The Importance of Flow,” “Drum-Buffer-Rope for High Mix,” “Full Kit and Accurate Information” and “Enabling Change.” The full article can be found here: http://www.thefabricator.com/article/forceos/high-mix-fast-delivery--on-time “Dr. Lisa” Lang is one of the foremost Theory of Constraints experts in the world and a sought after manufacturing expert having been named the 2012 Manufacturing Trendsetter in the USA Today for her inexpensive and guaranteed Velocity Scheduling System Coaching Program that has dramatically improved performance of well over 100 highly custom job shops and machine shops.  She has also appeared in CBS News, The Wall Street Journal, Finance.com, About.com, NY Daily News, CNBC, The Boston Globe, The Miami Herald, and others. She is active in helping reshore manufacturing back to the U.S. and in the NTMA, PMA, and AMT communities having helped member companies to reduce their lead-times and improve due date performance. She worked with Dr. Goldratt who is the father of Theory of Constraints and author of the bestselling book, The Goal.  Dr Lisa is the President of the Science of Business specializing in increasing profits of highly custom manufacturers by applying Theory of Constraints, Lean and Six Sigma to operations with Velocity Scheduling System and to engineering/design with Project Velocity System and to marketing with her Mafia Offer Boot Camp. Learn more about Dr. Lisa and job shop scheduling at https://www.velocityschedulingsystem.com/ and check out her 47-minute webinar “How To Get More Jobs Done Faster” at www.velocitySchedulingSystem.com/webinar/. ### Contact: Dr Lisa Lang President, Science of Business Inc DrLisa@ScienceofBusiness.com keywords: Dr Lisa Lang, Dr Lisa, Theory of Constraints, Velocity Scheduling System, high mix low volume, drum buffer rope, job shop scheduling, Goldratt Links: http://prlog.org/11996440 http://bit.ly/WSz4zB http://bit.ly/WSA4Ul

http://www.velocityschedulingsystem.com/?p=1492

Wednesday, May 31, 2017

Precision Machining Job Shop Scheduling Client Success Story

FOR IMMEDIATE RELEASE Manufacturing and Theory of Constraints Expert Dr. Lisa Lang Shares Client Success Story Tanya DiSalvo, President of Criterion Tool, shares her story of how her precision machine shop used Velocity Scheduling System to achieve record profits.   Green Valley, AZ – November 14, 2012 – “Dr. Lisa” Lang, President of the Science of Business and Theory of Constraints expert, is proud to share one of many client success stories. Tanya DiSalvo is the President of Criterion Tool (founded in 1953) and an active member of both NTMA (National Tooling and Machining Association) and PMPA (Precision Metal Products Association).  Tanya has utilized Dr. Lisa’s Velocity Scheduling System at her machine shop to improve on-time delivery and reduce lead times. Tanya DiSalvo’s case study and success story (written by Mike Touzeau) can be found at https://www.velocityschedulingsystem.com/site/wp-content/uploads/2012/10/Tanya_Success_Story_v5.pdf Here is an excerpt: “It’s so different from what we’ve seen in the world of manufacturing that it sounded too good to be true. At first as a team we couldn’t get our arms around it, but Dr. Lisa said she was going to give me my money back if it didn’t work, so we were going to do everything she said.” They liked the homework, but several of her 30 employees, including her dad, who was then  consulting and observing as he neared retirement, bet some real cash against her that it wasn’t going to work. “I was pretty sure they thought this was just another flavor of the month. Before VSS we were all frustrated,” she remembers, because they were always  trying to manage the “slop,” as she calls it—the jobs that got bogged down and often carried into the next month,  with select customers always suffering. Once they saw how the system could facilitate movement of jobs, things started clicking. “As we worked through the Velocity Scheduling process, we got more and more in control. We could focus our resources where we needed them the most. We didn’t have to monitor the jobs, the deadlines, the priorities anymore.” “It was all the  same people just changing their focus.” To learn specifically what Tanya did to improve her machine shop scheduling, watch a 47 minute webinar on “How to Get More Jobs Done Faster” at https://www.velocityschedulingsystem.com/webinar/ “Dr. Lisa” Lang is one of the foremost Theory of Constraints experts in the world and a sought after manufacturing expert having been named the 2012 Manufacturing Trendsetter in the USA Today for her inexpensive and guaranteed Velocity Scheduling System Coaching Program that has dramatically improved performance of well over 100 highly custom job shops and machine shops.  She has also appeared in CBS News, The Wall Street Journal, Finance.com, About.com, Gear Technology, CNBC, MoldMaking Technology, The Fabricator, NTMA’s The Record and many others. She is active in helping the reshoring of  manufacturing back to the U.S. and in the NTMA, PMA, and AMT communities having helped member companies to reduce their lead-times and improve due date performance. She worked with Dr. Goldratt who is the father of Theory of Constraints and author of the bestselling book, The Goal. Dr Lisa is the President of the Science of Business specializing in increasing profits of highly custom manufacturers by applying Theory of Constraints, Lean and Six Sigma (TLS) to operations with Velocity Scheduling System and to engineering/design with Project Velocity System and to marketing with her Mafia Offer Boot Camp. ### Contact: Dr Lisa Lang Science of Business, Inc DrLisa@ScienceofBusiness.com   keywords: Dr Lisa Lang, Dr Lisa, Theory of Constraints, Velocity Scheduling System, job shop scheduling, machine shop scheduling, Goldratt, reshoring manufacturing, Success Story, Case Study

http://www.velocityschedulingsystem.com/?p=1654

Sunday, May 28, 2017

Conventional Wisdom vs "Off the Shelf TOC" vs Velocity Scheduling System

Here is the second FREE Special Report on scheduling for custom job shops by Dr Lisa Lang. This report takes an in-depth look at the differences between conventional scheduling wisdom, "Off the Shelf TOC" (Traditional DBR & Simplified DBR scheduling), and the Velocity Scheduling System. I think you will find it enlightening. It's something that most TOC consultants don't even understand. Please leave your comments and questions after reading it. https://www.VelocitySchedulingSystem.com/ebook2/

http://velocityschedulingsystem.wordpress.com/?p=79

Job Shop Scheduling using the Velocity Scheduling System

I was interviewed about Theory of Constraints by Gear Technology magazine. You can read that article here: Theory of Constraints article by Dr Lisa Lang.

http://velocityschedulingsystem.wordpress.com/2009/05/10/job-shop-scheduling-using-the-velocity-scheduling-system/

Machine Shop gets BIG results with the Velocity Scheduling System

By Dr Lisa Lang Tanya DiSalvo, President of Criterion Tool & Die, just sent me this email:

Lisa & Brad- We finished off our fiscal year end 10/31..... could have never turned things around w/out the V V S.!!!!!! We finished the year in the black because 'the board' helped us focus on FINISHING! The last 6 months also saw a serious improvement in on time delivery, and an increase in the volume of orders thru our building. We have accepted a long running project, and feel that the self releasing mechanism of "The Board" has allowed us to tackle this type of work effectively while still serving our job shop type customers. No job gets lost in the shuffle no matter how longs its in the building, and the resources (people) have become utility ball players! I have included a snapshot since May of our numbers. Jumped back into Mafia Offer training.... Got the itch to know more!!! THANK YOU! Tanya DiSalvo Criterion Tool
And here are some of their key meterics: [caption id="" align="aligncenter" width="441"]The Velocity Scheduling System helps this machine shop get on time! The Velocity Scheduling System helps this machine shop get on time![/caption] Jobs spend less time in the shop -- job velocity increases! Criterion ships more $ with the Velocity Scheduling System! Criterion has almost doubled the dollars out the door. If you ship twice as much and you don't hire anyone or buy any equipment -- what happens to your profits? Tanya is now working on Criterion's Mafia Offer. Because by implementing the Velocity Scheduling System, they have uncovered capacity. So the next step is to sell that capacity. If you need to get your operations in order, you can sign up here: www.VelocitySchedulingSystem.com.  If registration is closed, you will have the opportunity to get on the waiting list to be notified if there is another session.

http://velocityschedulingsystem.wordpress.com/?p=281

Theory of Constraints Results After 1 Year

By Dr Lisa Lang You may remember these graphs from some reported results (a testimonial) on job shop scheduling below. [caption id="" align="aligncenter" width="441"]The Velocity Scheduling System helps this machine shop get on time! The Velocity Scheduling System helps this machine shop get on time![/caption] Jobs spend less time in the shop -- job velocity increases! Criterion ships more $ with the Velocity Scheduling System! Well I just got an update from Tanya. Here it is:

SUBJECT: Our One Year Anniversary “Welp it’s Criterion’s one year anniversary with the VSB (Velocity Scheduling System) and WE STILL love it! A few major projects went thru our building: new product launch in Oct- Dec, another new product launch currently under way, reduction of staff thru attrition and increase in work, and in most cases we came thru with flying colors. Attached is our score card. ”
Accenture just released a report in conjunction with the United Nations Global Compact called “A New Era of Sustainability.” The most significant finding was that 93% of the approximately 1,000 CEOs surveyed from across the globe indicated they believe sustainability is important to their companies’ future success. So if sustainability is important to you, maybe the Velocity Scheduling System Coaching Program is a good fit. The Velocity Scheduling System that Tanya uses is based on the Theory of Constraints Drum Buffer Rope. There are 1000s of success stories dating back to the 80s. Build -- Capitialize -- Sustain. We agree that sustainability is important. The key is how to achieve it. The answer is simple -- the Velocity Scheduling System Coaching Program.

http://velocityschedulingsystem.wordpress.com/?p=443

Manufacturing heads back to USA (reshoring) - USATODAY.com

This article in the USAToday on reshoring manufacturing back to the US is interesting and not at all surprising. Regarding this part of the article: "Products that are labor-intensive and churned out in high volumes, such as apparel, textiles and TVs, will likely continue to be made overseas. So will those that are relatively inexpensive to ship but high-priced, such as laptops and cellphones, Ellis says. Goods are increasingly being made near customers, a trend that's driving U.S. makers to build factories in fast-growing China." I did an RMTMA (Rocky Mountion Tooling and Machining Association) dinner presentation several years ago titled "China, India, Tawain ... Oh My!" and my contention then was (and still is) that the more flexible and custom you are as a manufacturer the more likely your work will stay here. The faster you can get highly custom work through your shop -- the more secure your future is. I suggest taking a look at the work you hate to do -- and figure out a way to make it easier, start loving it, and go get more of it because your competition hates it too! The shops participating in our Velocity Scheduling System program are seeing their lead-times cut by more than 50%. If they can have something ready to ship while everyone else is still complaining about it -- they are going to be extremely successful in the long run.

http://velocityschedulingsystem.wordpress.com/?p=461

R&D Tax Credit to Improve Job Shop Scheduling

The Tax Extenders Package signed by President Obama on December 17th, 2010 calls for a two year extension, retroactive to 1/1/10 and through 12/31/11 for the R&D Tax Credit. The definition of Research and Development (R&D) is much broader than people realize.  Activities and costs associated with developing and/or improving a product or process can potentially generate R&D Tax Credits. This means that your tuition for the Velocity Scheduling System Coaching Program may be covered -- check with your accountant. So learn a new way to run and schedule your shop, get on-time, get happy customers, get more customers --- and then get a tax credit!  How cool is that! And even if, for some reason, it doesn't apply to you.  Velocity Scheduing System Coaching Program is so reasonably priced it may not be worth the effort to look for a writeoff or funding. Now, the only other question you may have is --- Yes, but will Velocity Scheduling System work for me?  Will it work in my my shop with our unique situations and challenges? I don't know, because even though over a hundred highly custom job shops have had fantastic success, that doesn't mean you will.  But I'm willing to investigate it with you.  So if you'd like a private strategy session to discuss your company, your unique scheduling challenges and how/if our scheduling solution will work for you, you can sign up here, there's no charge:

https://www.VelocitySchedulingSystem.com/private

You'll need to enter your name and phone number so that we can call you to schedule a time to talk.  I am personally doing these sessions and we will be going deep into YOUR scheduling challenges.  I will hold nothing back and give you my best advice, even if it is that you should NOT sign up for VSS.  Time slots are limited SO SIGN UP NOW! Dr Lisa President, Science of Business
P.S. Sign up for the no charge strategy session here:  www.VelocitySchedulingSystem.com/private  This is your first step to getting on-time in 2011 and then to getting a tax credit!
P.P.S.  And some states have their own R&D Tax Credit too.  I know Ohio has one, so check with your accountant on that too.  But don't spend too much time, VSS typically pays back in a couple weeks.  It's based on the Theory of Constraints Simplified Drum Buffer Rope, and it works FAST!

http://velocityschedulingsystem.wordpress.com/?p=504

Michigan Precision Machine Shop Scheduling Success Story

FOR IMMEDIATE RELEASE

Manufacturing and Theory of Constraints Expert Dr. Lisa Lang Features a Michigan Precision Machine Shop Success Story

Robert Peuterbaugh, President of Joint Production Technology, shares his story of how the Velocity Scheduling System is helping his company to see increased production and profits. Green Valley, AZ – December 29, 2012 – “Dr. Lisa” Lang, President of the Science of Business and Theory of Constraints expert, is proud to share another client job shop scheduling success story.  Robert Peuterbaugh, president of Joint Production Technology (JPT) in Macomb, Michigan.  Robert has utilized Dr. Lisa’s Velocity Scheduling System to improve productivity at his facility. The Velocity Scheduling System is based on Theory of Constraints, but it has been adapted for highly custom job shops and machine shops whose constraint can move week-to-week or day-to-day. Robert Peuterbaugh’s case study and success story (written by Mike Touzeau) can be found at https://www.velocityschedulingsystem.com/site/wp-content/uploads/2012/12/VSS-success-1-v4.pdf Here is an excerpt:
Providing high tech innovations for precision cutting, boring, and other applicable manufacturing functions for such big outfits as GM, Ford, TRW, and many others here and abroad, Peuterbaugh knows his operation inside out. Battling the downturn like everyone else, this seasoned leader has always investigated long-term remedies rather than groping for gimmicks, so he began to search for solutions. “As things got worse, I looked at what would make things better,” he said.” I had followed Dr. Lisa’s emails for two years before signing up.” He knew it would be important to improve productivity, so having read much of what Dr. Lisa had written on Velocity Scheduling System (VSS), he took the plunge, knowing many others wouldn’t. “Sometimes you say that we’re good at what we do, so why change?” “When I saw all the reasons,” he put it, “it all fit. That’s what got me to talk to her.” JPT HAS SHOWN A 64 % INCREASE IN SHIPPED $. He estimates between a 25 and 35 percent profit increase “directly attributable,” he says, to the changes his team instituted after starting the VSS program in February. Once the process started working, he recalls, his team stood in awe at the seamless flow, shipping each day with customers getting something every day. “They just could not believe it.”
And another:
Robert Peuterbaugh’s story is probably not unlike your own. You worked hard to build a solid reputation with your customers. You want American manufacturing to be great, and though you’re a successful small or large operation, scheduling is still always an issue. VSS is a system that creates a continuous flow in your operation so all your employees share in knowing what needs to be done and when.
A member of many manufacturing organizations, Robert Peuterbaugh works with local schools to promote manufacturing career education, and serves on the Board of Directors for Tooling, Manufacturing & Technologies Association (TMTA). To learn specifically what Robert did to improve Joint Production Technology, watch a 47-minute webinar on “How to Get More Jobs Done Faster” at https://www.VelocitySchedulingSystem.com/webinar/  or read the “9 Challenges to Scheduling Your Job Shop” ebook at https://www.VelocitySchedulingSystem.com/ebook/.   “Dr. Lisa” Lang is one of the foremost Theory of Constraints experts in the world and a sought after manufacturing expert having been named the 2012 Manufacturing Trendsetter in the USA Today for her inexpensive and guaranteed Velocity Scheduling System Coaching Program that has dramatically improved performance of well over 100 highly custom job shops and machine shops.  She has also appeared in CBS News, The Wall Street Journal, Finance.com, About.com, Gear Technology, CNBC, MoldMaking Technology, The Fabricator, NTMA’s The Record and many others. She is active in helping the reshoring of  manufacturing back to the U.S. and in the NTMA, PMA, and AMT communities having helped member companies to reduce their lead-times and improve due date performance. She worked with Dr. Goldratt who is the father of Theory of Constraints and author of the bestselling book, The Goal. Dr Lisa is the President of the Science of Business specializing in increasing profits of highly custom manufacturers by applying Theory of Constraints, Lean and Six Sigma (TLS) to operations with Velocity Scheduling System and to engineering/design with Project Velocity System and to marketing with her Mafia Offer Boot Camp.   ### Contact: Dr Lisa Lang Science of Business, Inc DrLisa@ScienceofBusiness.com   keywords: Dr Lisa Lang, Dr Lisa, Theory of Constraints, Velocity Scheduling System, job shop scheduling, machine shop scheduling, Goldratt, reshoring manufacturing, Success Story, Case Study, TMTA, Michigan Manufacturer   Links: http://prlog.org/12050614 http://www.pressnewsroom.com/?p=18180 http://bit.ly/Wbxt5w

http://www.velocityschedulingsystem.com/?p=1666

Job Shop and Machine Shop Profitability part 2

  This is the second in the series of conversations. Brad:  “Just what should a highly custom job shop or machine shop company set as a profitability goal?  What is reasonable?  How high is up?” Dr. Lisa:  “I’ll give you Dr Eliyahu Goldratt’s answer and then I give my more direct answer.  Dr. Goldratt stated that profitability goal of the business should be a level of return on sales that top management of a company agrees is definitely impossible to attain.” Dr. Lisa:  “For example, if everyone agrees that 5% Return of Sales is definitely possible, that is too low of a goal.  If everyone feels the same about 6%, 7%, 8%, and 9%, they those levels are also too low of a goal.  But if everyone agrees that 10% is not achievable, that then becomes the goal.” Brad:  “That would be an interesting exercise for any CEO to do with his or her top management team.” Dr Lisa:  “My answer:  How high is up is going to be dependent on 1) what percent your Truly Variable Costs (TVCs) are of sales.  And 2) how much capacity you can undercover – meaning how much productivity you can gain with the same people and resources.” Dr Lisa:  Knowing both of these numbers (better to be approximately right, than precisely wrong), will allow you to arrive at a very feasible goal and yet one that most will agree is not attainable based on previous experience.” Dr Lisa:  Using the same example from our last conversation, I’ve added the Return on Sales:

Job Shop Profit Return on Sales

We’ve gone from 0% Return on Sales to 8.3% Return on Sales by being able to sell the 20% productivity gain that was achieved. Brad:  “Many job shops and machine shops that we work with have 20 to 35% TVCs (which typically includes raw materials, outside services, and sales commission if any).  Some more some less, but this is common.  When I initially analyze the financials of a company, I’m looking for the actions and implementation steps required to bring the company to reliably make a 20% Return on Sales month in and month out, year in and year out.” Dr. Lisa:  “Ha!  Be careful, you’ll scare some business owners with that goal.  He or she will definitely think that goal is unattainable!” Brad:  “A small business making 20% Return on Sales is a lot more fun to run than a larger business barely managing to reach breakeven.” Dr. Lisa:  “For sure.  A company with sales of $2.5 million and a 20% Return on Sales has $500,000 of net income.  And so does a company with $25 million of sales with a measly 2% Return on Sales”. Brad:  “Now the nifty thing is that TOC ‘silver bullets’ can be used with that same company with $25 million in sales to bring them to achieve a 20% Return on Sales – a jump from $500,000 to $5 million of net profit.” Dr. Lisa:  “Yes, no wonder that Merger & Acquisition and Turnaround Management Professionals are showing a lot of interest in TOC.” Brad:  “Okay, so let’s discuss more about how this fantastic improvement just might be possible…” To be continued. Best Wishes, Dr Lisa and Brad Stillahn P.S.  To ask questions or leave a comment go below this post. P.P.S. To find out more about improving productivity in highly custom job shops and machine shops, take a tour around this site.  You'll want to check out the job shop scheduling ebook and the webinar. P. P.P.S. If you have plenty of capacity, but can’t sell it, visit www.MafiaOffers.com. By Dr Lisa Lang and Brad Stillahn This article is copyrighted by Science of Business, Inc. Visit our Re-post guidelines.

http://www.velocityschedulingsystem.com/?p=1761

Job Shop Scheduling for a Custom Material Handling Equipment Manufacturer

By Dr Lisa Lang Here's yet another Velocity Scheduling System testimonial.  This highly custom job shop makes custom material handling equipment.

"We have reduced the time that it takes for a job to go through the shop.  It helped us get control of the schedule, by reducing the scramble of jobs in the shop.  Now we do them in order and everyone in the company knows when to expect a job to be worked on and ready to ship."  Steve, WI.
If you browse the various VSS testimonials, case studies, and results that custom job shops have reported you'll discover that none of the VSS clients are making widgets. None of these shops are doing high volume work of the same widgets over and over. One thing that VSS clients have in common is that they do NOT produce the same things over and over again.  While some jobs, may on occasion, repeat for some of them (or they may make a few things to stock), others don't do any repeat work at all. Job shop scheduling in a custom manufacturing shop is a challenge, to say the least!  But it is this environment that Velocity Scheduling System was developed for. You'll also notice that in some of the testimonials the specific shop is NOT identified.  Why?  Well, Steve in WI and many others don't want their competitors to know how they've managed to gain a competitive advantage.  How is it that they can get more jobs done faster with the same people and resources?  How is it that they've improved on time delivery?  How are they more cash flush and more profitable? To get the results that Steve got or that any of our clients have gotten, you don't need any job shop scheduling software.  VSS is NOT software.  It is a manual, visual scheduling system.  It will work with any ERP software you may use, no ERP, QuickBooks, Excel or whatever software your using now.

http://www.velocityschedulingsystem.com/?p=1815

The Goal by Goldratt is on Amazon Top Executives Book Club

By Dr Lisa Lang

This article is copyrighted by Science of Business, Inc. 2013

Visit our Re-post guidelines.

In an interview with Amazon CEO Jeff Bezo, Jon Fortt for CNBC reported:
 This summer he (Amazon CEO Jeff Bezo) spent time at Lab126, a Silicon Valley outpost about a mile from Apple headquarters where Amazon engineers hash out hardware designs. And he also hosted three all-day book clubs with Amazon's top executives, capped by nice dinners at the end. Bezos said he used the books as frameworks for sketching out the future of the company.The Goal flat Which books? Bezos was kind enough to share the titles. Read the entire story here:  https://www.linkedin.com/pulse/20130925133311-291225-amazon-ceo-jeff-bezos-had-his-top-execs-read-these-three-books
The Goal was originally published in 1984 but is still very relevant today.  And, as you likely know, it take place in a machine shop.  Many job shops and machine shops use The Goal as their Bible.  The only problem is that most have no idea how to apply it to their unique shop. Well, I have good news.  If you own or manage a highly custom job shop or machine shop and want to apply what you read in The Goal to YOUR shop, you can do that with expert guidance very inexpensively.  Just check out the Velocity Scheduling System (VSS)  Coaching Program. VSS is NOT software but a visual manual scheduling system developed specifically for highly custom job shops and machine shops which are typically low volume high mix environments where the constraint can move week to week or even day to day. Who's the expert that would guide you?  Well that's Dr Lisa Lang.  She is one of the foremost Theory of Constraints experts who has worked with Dr Goldratt and specializes in applying Theory of Constraints to highly custom job shops and machine shops. Check out Velocity Scheduling System here:  www.VelocitySchedulingSystem.com When you're there check out the free webinar called "How to Get More Jobs Done Faster".  You'll be glad you did!

http://www.velocityschedulingsystem.com/?p=1837